[MAINTENANCE] VIC-IX | Equinix ME1 | 10G Port Migration

Scheduled for May 26, 14:00 - 20:00 UTC

Scheduled

IAA Engineers will be migrating all 10G ports at Equinix ME1 to new hardware to enhance PoP capacity.

Start: 27/May/2025 00:00 (AEST)
End: 27/May/2025 06:00 (AEST)
Window: 6 hours
Expected downtime: Up to ~15 minutes per port

Members with 10G service ports connected at Equinix ME1 should expect their port to go down during this window for up to 15 minutes, affecting all services associated with the port.

Ports will be drained of peering traffic using BCP214 compliant filters before they are migrated. Filters will be removed once the ports are back online and stable.

The work is expected to take about 3 hours. However, 6 hours has been booked in the unlikely event of an emergency.

If you have any questions or concerns regarding this notice, please contact us on 1300 793 320 or noc@ix.asn.au.
Posted May 08, 2025 - 02:00 UTC
This scheduled maintenance affects: Peering Fabric (VIC-IX).