[MAINTENANCE] WA-IX | QV1, Equinix PE2 | Firmware Upgrades and IGP Changes
Scheduled Maintenance Report for Internet Association of Australia
Completed
The scheduled maintenance has been completed.
Posted Mar 14, 2023 - 20:49 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 14, 2023 - 19:00 UTC
Scheduled
IAA Engineers will be upgrading the firmware of the remaining switching hardware across WA-IX to resolve several software bugs and additionally begin flattening the OSPF domain with other states to follow.

Window: 3 hours
Expected Downtime: ~15 minutes per site
Impacted sites: QV1, Equinix PE2

* Members with service ports at the above sites should expect their port to go offline for up to ~10 minutes whilst each switch is being upgraded.

Service ports will be drained of peering traffic roughly 5 minutes before their respective upgrades using BCP214 compliant filters. Filters will be removed once the devices are back online and stable.

* We will ensure at least one (1) route server is up at ALL times during the window. Please verify you are peering with both route servers to minimise the impact:

RS1 - 198.32.212.1/24 & 2001:7fa:11::1db6:0:1/64
RS2 - 198.32.212.254/24 & 2001:7fa:11::1db6:0:2/64


The work is expected to take about 1 hour. However, 3 hours have been booked in the unlikely event of an emergency.

If you have any questions or concerns regarding this notice, please contact us on 1300 793 320 or noc@ix.asn.au.
Posted Mar 01, 2023 - 06:20 UTC
This scheduled maintenance affected: Inter-Capital Network (PER-ADL) and Peering Fabric (WA-IX).